Road Construction Updates

Contact Information

Road and Highway Builders, LLC (RHB)  775-753-9512
Brian Martinez, RHB Area Manager 775-843-4645
bmartinez@roadandhighwaybuilders.com

NDOT Crew 918 Field Office 775-777-1168
NDOT District 3 Office  775-777-2700
Casey Kelly, NDOT Resisdent Engineer  775-777-1168
clkelly@dot.state.nv.us

Next Public outreach meeting

Public Outreach 
 Elko City Hall, 1751 College Ave.

Thursday   July 10th at 2:30pm
Wednesday   July 16th at 2:30pm
Wednesday   July 23rd at 2:30pm
Wednesday   July 30 at 2:30pm

Project updates 

***HAPPENING NOW***

NDOT 3550 Elko Urban Improvement Project will be shut-down from Friday, May 23, 2014 through Monday, May 26, 2014 due to the Memorial holiday. No lane restrictions will be in effect during this shut-down. 


IDAHO STREET: (Night Work)  Monday - Thursday  7:00pm - 6:00am
- Replace curb and gutter, handicap ramps & driveways

IDAHO STREET: (Day Work) Tuesday - Friday 6:00am - 6:00pm 
- Asphalt paving mainline & approaches
- Profile grinding AC pavement
- Extend reinforced concrete drainage boxes

MTN CITY HIGHWAY (Night Work): Monday-Thursday 7:00 pm - 6:00 am 
- Electrical work for signal systems
- Remove curb & gutter

LAMOILLE HIGHWAY: Monday-Friday Southbound 3am-4pm, Northbound 5am-5pm
-Mill and pave from Pinion Road to Jiggs/Spring Creek Parkway Intersection (Monday)
- Profile grind AC pavement 

completed WORK

  • Directional boring for electrical upgrades
  • Trenching for electrical upgrades on Mtn City Highway and 5th Street
  • Shoulder flattening on Lamoille Hwy
  • Crushing of asphalt aggregates and approval of asphalt mix designs 
  • I-80 Elko West NDOT maintenance salt sand pad reconstruction 

Project map