Road Construction Updates

Contact Information

Road and Highway Builders, LLC (RHB)  775-753-9512
Brian Martinez, RHB Area Manager 775-843-4645
bmartinez@roadandhighwaybuilders.com

NDOT Crew 918 Field Office 775-777-1168
NDOT District 3 Office  775-777-2700
Casey Kelly, NDOT Resisdent Engineer  775-777-1168
clkelly@dot.state.nv.us

Next Public outreach meeting

Public Outreach 
 Elko City Hall, 1751 College Ave.

Wednesday, October 8th @ 2:30
Wednesday, October 15th @ 2:30
Wednesday, October 22nd @ 2:30
Wednesday, October 29th @ 2:30

Project updates 

***WEEK OF OCTOBER 13th***

IDAHO STREET: (Day Work) Monday - Friday 7 am - 5 pm
- Drainage and shoulder work
- Permanent Striping (Thursday)

LAMOILLE HWY (Day Work) Wednesday - Thursday 8 am - 4 pm 
- Permanent Striping from Errecart Blvd to 12th Street 

MOUNTAIN CITY HIGHWAY (Night Work): Sunday - Thursday 7 pm - 6 am
- Replace curb/gutter, handicap ramps, driveways and sidewalks
- Asphalt patching

completed WORK

  • Directional boring for electrical upgrades
  • Trenching for electrical upgrades on Mtn City Highway and 5th Street
  • Shoulder flattening on Lamoille Hwy
  • Crushing of asphalt aggregates and approval of asphalt mix designs 
  • I-80 Elko West NDOT maintenance salt sand pad reconstruction 
  • Idaho Street concrete and drainage work
  • Idaho Street asphalt paving
  • Lamoille Highway asphalt paving (from 12th Street to Jiggs Hwy Intersection)
     

Project map