Road Construction Updates

Contact Information

Road and Highway Builders, LLC (RHB)  775-753-9512
Brian Martinez, RHB Area Manager 775-843-4645
bmartinez@roadandhighwaybuilders.com

NDOT Crew 918 Field Office 775-777-1168
NDOT District 3 Office  775-777-2700
Casey Kelly, NDOT Resisdent Engineer  775-777-1168
clkelly@dot.state.nv.us

Next Public outreach meeting

Public Outreach 
 Elko City Hall, 1751 College Ave.

Wednesday, August 27th @ 2:30
Wednesday, September 3rd @ 2:30
Wednesday, September 10th @ 2:30
Wednesday, September 17th @ 2:30
Wednesday, September 24th @ 2:30
Wednesday, October 1st @ 2:30


 

Project updates 

***HAPPENING NOW***

IDAHO STREET: (Night Work)  Tuesday - Thursday  7:00pm - 6:00am
- Mill & Asphalt Pave Roadway

MTN CITY HIGHWAY (Night Work): Tuesday - Thursday 7:00 pm - 6:00 am 
- Electrical work for signal upgrades
- Replace curb/gutter, handicap ramps, driveways and sidewalks

LAMOILLE HIGHWAY ( Night Work): Tuesday - Thursday  8:00 pm - 5:00 am
- Install electrical sensors in roadway
- Profile and grind roadway
 

completed WORK

  • Directional boring for electrical upgrades
  • Trenching for electrical upgrades on Mtn City Highway and 5th Street
  • Shoulder flattening on Lamoille Hwy
  • Crushing of asphalt aggregates and approval of asphalt mix designs 
  • I-80 Elko West NDOT maintenance salt sand pad reconstruction 
  • Mainline paving Lamoille Summit 
     